Shipyards · Pascagoula, MS

Bollinger Mississippi Shipbuilding

Former VT Halter Marine yard bought by Bollinger in 2022; it is building the first Polar Security Cutter, USCGC Polar Sentinel, with 33 of 85 modules under construction as of July 2026. The Coast Guard targets delivery in FY2030; a June 2026 GAO report projected 2033.

Owner
Bollinger Shipyards
Type
New construction
Ownership
Private
Segments
Coast Guard
Workforce
—
Website
www.bollingershipyards.com

Hulls built here

HullNameProgramStatusLaunchedDeliveredPlanned deliverySource
WMSP-21Polar SentinelPolar Security Cutter (PSC)Under construction——2030Source
WMSP-22Polar BearPolar Security Cutter (PSC)Ordered——2032Source
WMSP-23Polar GlacierPolar Security Cutter (PSC)Planned——2034Source

Capital projects

Polar Security Cutter production integration and land-based test facilities

Cost not disclosed · Announced · target 2027 · funding: mixed

On July 23, 2025 the Coast Guard modified the first Polar Security Cutter construction contract to fund a production integration facility and a land-based test facility at Bollinger's Pascagoula yard through capital expenditure incentives. A $33.1 million modification for long-lead material for both facilities followed on Dec. 18, 2025, with work expected through September 2027.