Polar Security Cutter (PSC)

Contracted to Halter Marine (now Bollinger Mississippi) in April 2019; the first ship, originally due in 2024, is projected no earlier than 2030 (CRS, January 2026). In August 2026 USNI reported 33 of 85 modules for Polar Sentinel under construction, with the Coast Guard targeting FY2030 while a June 2026 GAO report projected 2033.

Type
Heavy polar icebreaker
Status
In production
Planned quantity
3
Unit cost
—
Builders
Bollinger Shipyards

Hulls

HullNameBuilder yardStatusLaunchedDeliveredPlanned deliverySource
WMSP-21Polar SentinelBollinger Mississippi ShipbuildingUnder construction——2030Source
WMSP-22Polar BearBollinger Mississippi ShipbuildingOrdered——2032Source
WMSP-23Polar GlacierBollinger Mississippi ShipbuildingPlanned——2034Source