Shipyards · Bremerton, WA

Puget Sound Naval Shipyard & Intermediate Maintenance Facility

The command provides maintenance, modernization, recycling and support for Navy ships and runs the Trident Refit Facility at Bangor; the CNO toured Dry Docks 3 and 4 on June 3, 2026. Structural upgrades to its dry docks are ongoing under the Navy's shipyard infrastructure program.

Owner
U.S. Navy (NAVSEA)
Type
Repair
Ownership
Public (Navy)
Segments
Navy
Workforce
—
Dry docks
Multiple graving docks including Dry Docks 3 and 4 (total count not verified)
Website
www.navsea.navy.mil/Home/Shipyards/PSNS-IMF/

Hulls built here

No hulls recorded.

Capital projects

Dry Dock 4 seismic upgrade (next phase)

$377.7M · Under construction · funding: Navy SIOP

On Sept. 2, 2025 NAVFAC Northwest awarded a $377.7 million task order to Kiewit-Alberici Joint Venture to continue seismic upgrades of Dry Dock 4, which supports nuclear submarine maintenance, extending wall-anchor work begun in 2023.

Electrical substation replacement

$145M · Under construction · target 2029 · funding: Navy SIOP

On Sept. 16, 2024 NAVFAC Northwest awarded Absher Construction a $145 million SIOP task order to replace an aging PSNS electrical substation with two 40/60 MVA substations and supporting infrastructure; local reporting said work is planned to run through 2029.

Multimission Dry Dock (Dry Dock 3 / Piers 6-7 footprint)

Cost not disclosed · Announced · funding: Navy SIOP

WSM Pacific SIOP JV received an $8.1 million architect-engineer task order in February 2022 for early design of a new multimission dry dock at PSNS. In June 2026 the Navy issued a presolicitation for a multiple award construction contract with a $30 billion ceiling covering the dry dock (able to service Ford- and Nimitz-class carriers) and related work, with MACC awards targeted for May 2027.