As of March 2026 the 86-acre Barrio Logan yard (about 3,500 employees) had christened the last ESB, USNS Hector A. Cafferata Jr., and continued building John Lewis-class fleet oilers under a September 2024 contract for up to eight more ships (T-AO 214 to 221).
- Owner
- General Dynamics NASSCO
- Type
- Build and repair
- Ownership
- Private
- Segments
- Navy, Commercial
- Workforce
- 3,500
- Website
- nassco.com
Hulls built here
| Hull | Name | Program | Status | Launched | Delivered | Planned delivery | Source |
|---|---|---|---|---|---|---|---|
| T-AO-207 | Earl Warren | John Lewis (T-AO-205) class | Delivered | 2022-10-28 | 2024-05-07 | — | Source |
| T-AO-208 | Robert F. Kennedy | John Lewis (T-AO-205) class | Delivered | 2023-10-29 | 2024-12-10 | — | Source |
| T-AO-209 | Lucy Stone | John Lewis (T-AO-205) class | Delivered | 2024-09-21 | 2025-12-16 | — | Source |
| T-AO-210 | Sojourner Truth | John Lewis (T-AO-205) class | Delivered | 2025-04-26 | 2026-06-09 | — | Source |
| T-AO-211 | Thurgood Marshall | John Lewis (T-AO-205) class | Launched | 2026-04-18 | — | — | Source |
| T-AO-212 | Ruth Bader Ginsburg | John Lewis (T-AO-205) class | Under construction | — | — | — | Source |
| T-AO-213 | Harriet Tubman | John Lewis (T-AO-205) class | Under construction | — | — | — | Source |
| T-AO-214 | Dolores Huerta | John Lewis (T-AO-205) class | Under construction | — | — | — | Source |
| T-AO-215 | Joshua L. Goldberg | John Lewis (T-AO-205) class | Under construction | — | — | — | Source |
| T-AO-216 | Thomas D. Parham | John Lewis (T-AO-205) class | Ordered | — | — | — | Source |
| T-AO-217 | — | John Lewis (T-AO-205) class | Ordered | — | — | — | Source |
| T-AO-218 | — | John Lewis (T-AO-205) class | Planned | — | — | — | Source |
| T-AO-219 | — | John Lewis (T-AO-205) class | Planned | — | — | — | Source |
| T-AO-220 | — | John Lewis (T-AO-205) class | Planned | — | — | — | Source |
| T-AO-221 | — | John Lewis (T-AO-205) class | Planned | — | — | — | Source |
| ESB-7 | Robert E. Simanek | Lewis B. Puller (ESB) class Expeditionary Sea Base | Delivered | — | 2024-09-12 | — | Source |
| ESB-8 | Hector A. Cafferata Jr. | Lewis B. Puller (ESB) class Expeditionary Sea Base | Delivered | — | 2026-08-25 | — | Source |
Capital projects
Replacement floating dry dock (35,000-ton)
NASSCO took delivery in August 2025 of a new 830 by 177 ft, 35,000-ton floating dry dock built by Gemak in Turkey, replacing the 40-year-old NASSCO Builder and able to dock any Navy ship except Nimitz-class carriers. As of January 2026 it was installed but not yet commissioned, with USS America planned as its first job; cost was not reported.