Sentinel (WPC-1101) class Fast Response Cutter

On September 10, 2025 the Coast Guard awarded Bollinger a $507 million option for 10 more FRCs using OBBBA funds, bringing the total procured to 77 and extending the line by about three years; 61 had been accepted by October 23, 2025.

Type
Fast response cutter (patrol)
Status
In production
Planned quantity
77
Unit cost
—
Builders
Bollinger Shipyards

Hulls

HullNameBuilder yardStatusLaunchedDeliveredPlanned deliverySource
WPC-1156David DurenBollinger LockportDelivered—2024-03-14—Source
WPC-1157Florence FinchBollinger LockportDelivered—2024-06-13—Source
WPC-1158John WitherspoonBollinger LockportDelivered—2024-11-07—Source
WPC-1159Earl CunninghamBollinger LockportDelivered—2025-03-06—Source
WPC-1160Frederick MannBollinger LockportDelivered—2025-06-16—Source
WPC-1161Olivia HookerBollinger LockportDelivered—2025-10-23—Source
WPC-1162Vincent DanzBollinger LockportDelivered—2026-02-26—Source
WPC-1163Jeffrey PalazzoBollinger LockportDelivered—2026-06-11—Source
WPC-1164Marvin PerrettBollinger LockportDelivered—2026-09-10—Source
WPC-1165Frank DeVitaBollinger LockportUnder construction——2026Source
WPC-1166—Bollinger LockportOrdered——2028Source
WPC-1167—Bollinger LockportOrdered——2028Source