The first ship was procured in FY2022 and the FY2026 budget requested $612.2 million for the second; the Navy's FY2026 budget shows lead ship delivery in July 2031. GAO reported in June 2025 that functional design was only 12% complete as of October 2024 and no construction start date was set; CBO estimated $900 million per ship versus the Navy's $450 million.

Type
Ocean surveillance ship (T-AGOS, SWATH)
Status
In design
Planned quantity
7
Unit cost
—
Builders
Austal USA

Hulls

HullNameBuilder yardStatusLaunchedDeliveredPlanned deliverySource
T-AGOS-25—Austal USA Mobile ShipyardOrdered——2031-07Source